Title: Approval of waiver of bidding requirements set forth in Article V, Section c. and Article XIV of the City of Broken Arrow Purchasing Manual and issuance of a purchase order for the purchase of storm drainage piping from DP Supply Co. for the Washington Street Improvements from Garnett Road to Olive Avenue construction project (ST1616B)
Attachments: 1. ST1616B – DP Supply HP Pipe Proposal 9-30-2020
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Broken Arrow City Council
Meeting of: 10-06-2020

Title:
title
Approval of waiver of bidding requirements set forth in Article V, Section c. and Article XIV of the City of Broken Arrow Purchasing Manual and issuance of a purchase order for the purchase of storm drainage piping from DP Supply Co. for the Washington Street Improvements from Garnett Road to Olive Avenue construction project (ST1616B)
End

Background:
The attached requested quote for materials encompasses the supply of high density polypropylene (HDPE) HP Storm pipe for the project ST1616B in which the Streets and Stormwater Department personnel will install the pipe associated with construction of the roadway widening project along Washington Street from Garnett Road (113th East Avenue) to Olive Avenue (129th East Avenue).

As a part of the ST1616 public construction contract executed between the City and Broken Arrow (COBA) and H&G Paving, Inc. (Contractor), the Contractor entered into an agreement with DP Supply Co. to provide above identified materials. During the course of the project, COBA and the Contractor executed a Change Order to reduce the scope of work, with the exception of the traffic signaling work and traffic control services. With this Change Order, the Contractor demobilized equipment, personnel, and vacated the project site, but left onsite the uninstalled HP Storm piping purchased from DP Supply. In order for the City to install the remaining HP storm pipe, a new contract is required between COBA and DP Supply Co for the remaining pipe. It should be noted that the Contractor was not paid for the product since it was not installed.

As a part of the deductive Change Order, the City verified the quantity of the HP Storm piping remaining onsite. September 15, 2020, DP Supply Co. also verified the amount of uninstalled HP Storm pipe remaining onsite. The two entities reviewed and confirmed the quantity remaining.

Below is the agreed upon amount of HP Storm Pipe remaining onsit...