Title: Approval of and authorization to execute Change Order #1 with Cherokee Pride Construction on Construction Contract ST1921; Detroit Street 3rd to 9th Street Rehabilitation
Attachments: 1. Change Order CO1, 2. ST1947-Detroit from 1st to 3rd Complete Final Plan Set
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Broken Arrow City Council
Meeting of: 5-5-2020

Title:
title
Approval of and authorization to execute Change Order #1 with Cherokee Pride Construction on Construction Contract ST1921; Detroit Street 3rd to 9th Street Rehabilitation

End

Background:
In March of 2018, the City Council ratified the Mayor's signing an application for Fiscal Year 2018 Tulsa County Urban Community Development Block Grant (CDBG) funds for Detroit Street from 4th Street to 9th Street. Subsequently, in May of 2019, the City Council ratified the Mayor's signing an application for Fiscal Year 2019 Tulsa County Urban Community Development Block Grant (CDBG) funds for Detroit Street from 1st Street to 4th Street. These projects will benefit the College Addition, a low to moderate income neighborhood. INCOG submitted the Contracts for Public Improvements for the street rehabilitation projects stated above.
Engineering and Construction staff undertook and completed design of a project on Detroit from 3rd Street to 9th Street. The design was extended westward from 4th Street to 3rd Street in order to facilitate proper drainage of the project. The project incorporates the following: an asphalt mill and overlay of the existing street, addition of sidewalks on both the north and south sides of Detroit, repair of approximately 483 linear feet of existing sanitary sewer, as well as incidental driveway and storm drainage construction. The project was advertised on October 14th with bids opened on November 12, 2019.The lowest responsible bidder was Cherokee Pride Construction, Inc., with a Total Bid of $517,733.50. Subsequently a Notice to Proceed to the contractor on January 13, 2010.

This Change Order #1 addresses the following additions to the contract:

- As directed by The City of Broken Arrow and agreed upon by the contractor, the contractor shall construct the Detroit Street 1rst to 3rd street rehabilitation project ST1947 as part of the current project. The attached plans shall be incor...

Click here for full text