File #: 24-565    Name:
Type: General Business Status: Agenda Ready
File created: 4/23/2024 In control: Drainage Advisory Committee
On agenda: 4/29/2024 Final action:
Title: Consideration, discussion, and possible action to recommend to City Council to expend funds to construct storm sewer on Dallas Street between 2nd Street and Haskell Park and repair adjacent properties (Case No. 24-010)
Attachments: 1. 24-010 DALLAS ST PACKET
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow Drainage Advisory Committee

Meeting of: 04/29/24

 

Title:

title

Consideration, discussion, and possible action to recommend to City Council to expend funds to construct storm sewer on Dallas Street between 2nd Street and Haskell Park and repair adjacent properties    (Case No. 24-010)

End

 

Background:

The storm sewer along the south side of East Dallas St between South 2nd St and South 4th St is corrugated metal pipe (CMP) and is estimated to have been installed between 1970 and 1990.  Residents in the area have contacted the City about potential issues with the storm sewer in relation to holes forming around their driveways.

Staff investigated the site while it was raining.  The holes were noted to be about in the same location as the storm sewer.  The CMP was visible in one of the holes.  Staff also sent a camera through the line.  The video showed some separation of the pipe at the joints and areas water the bottom has rusted out.

This item was presented to the DAC in March 2023 Case 23-001 for design.

Further investigation after the design in April 2024 has revealed continued infrastructure deterioration.

The City has already secured $256,122.00 from other sources for this project.

Staff is requesting $155,000.00 of unnamed Proposition 6 funds to construct the storm sewer line from South 2nd St to Haskell Park and repair adjacent properties.

This area flows to Haikey Creek.

 

Cost:                                                                $155,000.00

Funding Source:                     2018 GO Bond, Proposition 6

Requested By:                      Charlie Bright, P.E., Director of Engineering and Construction

Approved By:                      City Manager’s Office

Attachments:                                          Drainage Report, Exhibits   

 

Recommendation:

recommend

Recommend to City Council the expenditure of $155,000.00 to construct the storm sewer on Dallas Street between South 2nd Street to Haskell Park and repair adjacent properties.

end