LEGISLATIVE RESEARCH CENTER
File #: 24-563    Name:
Type: General Business Status: Agenda Ready
File created: 4/23/2024 In control: Drainage Advisory Committee
On agenda: 4/29/2024 Final action:
Title: Consideration, discussion, and possible action to recommend to City Council to expend funds to design erosion control measures along the bank of Haikey Creek at the Diocese of south Tulsa (Case No. 24-007)
Attachments: 1. 24-007 Diocese
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow Drainage Advisory Committee

Meeting of: 04/29/24

 

Title:

title

Consideration, discussion, and possible action to recommend to City Council to expend funds to design erosion control measures along the bank of Haikey Creek at the Diocese of south Tulsa (Case No. 24-007)

End

 

Background:

The proposed project at 12300 E 91st St is to design erosion control measures along the bank of Haikey Creek near the Diocese of South Tulsa. 

Staff investigated the site and found that the bank of Haikey Creek, south of Washington Ave was eroding on the Diocese property.

The four-cell box culvert under Washington Ave (91st) near the Diocese of Tulsa in Broken Arrow was widened during the roadway widening project.  The construction/widening of the boxes was completed, but the armoring did not take place. The armoring project was bid out by the City in 2021, but did not receive any bids.

The increased velocity has caused the south bank of Haikey creek to erode. The project will be to clean the box culvert, the north channel, and to design erosion control measures armor the southern bank.  

The estimated design cost to engineer a erosion control measures is approximately $50,000.00 in 2024 Dollars.

Staff is requesting $50,000.00 of the 2018 GO Bond, Proposition 6 for design costs.

This area flows to Haikey Creek.

 

Cost:                                                                $50,000.00

Funding Source:                     2018 GO Bond, Proposition 6

Requested By:                      Charlie Bright, P.E., Director of Engineering and Construction

Approved By:                      City Manager’s Office

Attachments:                                          Drainage Report, Exhibits   

 

Recommendation:

recommend

Recommend to City Council the expenditure of $50,000.00 for funds to design erosion control measures along the bank of Haikey Creek.

end