LEGISLATIVE RESEARCH CENTER
File #: 21-453    Name:
Type: Consent Item Status: Agenda Ready
File created: 3/29/2021 In control: Broken Arrow City Council
On agenda: 4/6/2021 Final action:
Title: Award the lowest responsible bid to Cherokee Pride Construction, Inc., and approve and authorize execution of a construction contract for Concrete Roadway Panel Replacement With Additional Miscellaneous Concrete Work for: Aspen Pond Subdivision (ST21200), Westwind Subdivision (ST21180), & Granger Street (ST21250)
Attachments: 1. ST21200,ST21180,ST21250 Bid Tab signed
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Broken Arrow City Council
Meeting of: 04-06-2021

Title:
title
Award the lowest responsible bid to Cherokee Pride Construction, Inc., and approve and authorize execution of a construction contract for Concrete Roadway Panel Replacement With Additional Miscellaneous Concrete Work for: Aspen Pond Subdivision (ST21200), Westwind Subdivision (ST21180), & Granger Street (ST21250)
End

Background:
The project includes the following:
SCHEDULE A - ST21200 - ASPEN POND: This project consists of the removal and re-construction of approximately 5,450 Square Yards of concrete roadway panels along with miscellaneous concrete work including sidewalk, curb and gutter, and ADA ramps. This roadway re-habilitation is located in the Aspen Pond subdivision between New Orleans Street and Washington Street and between Aspen Avenue and Elm Place in Broken Arrow, OK.
SCHEDULE B - ST21180 - WESTWIND SUBDIVISION: This project consists of the removal and re-habilitation of approximately 2,660 Square Yards of concrete roadway panels along with miscellaneous concrete work including sidewalk, curb and gutter, and ADA ramps. This roadway re-construction will be located in the Westwind subdivision between Kenosha Street and Albany Street and between 9th Street and 23rd Street in Broken Arrow, OK.
SCHEDULE C - ST21250 - GRANGER STREET: This project consists of the removal and re-habilitation of approximately 2,740 Square Yards of concrete roadway panels along with miscellaneous concrete work including sidewalk, curb and gutter, and ADA ramps. This roadway re-construction will be located on West Granger Street between Albany Street and Omaha Street and Aspen Avenue and Elm Place in Broken Arrow, OK.
The project was advertised on March 1 and 8, 2021. Bids were opened on March 30, 2021 with six (6) bids received and all being responsive. The Certified Bid Tabulation is attached. The bids submitted were composed of thirty five (35) pay items to form the Total Base Bid. The lowest responsible bid...

Click here for full text