LEGISLATIVE RESEARCH CENTER
File #: 20-1293    Name:
Type: Consent Item Status: Agenda Ready
File created: 10/12/2020 In control: Broken Arrow Municipal Authority
On agenda: 10/20/2020 Final action:
Title: Approve and authorize execution of an a agreement with Jacobs Engineering Group to provide Professional Engineering Services for the Risk and Resiliency Project (Project Number 2154090)
Attachments: 1. Agreement BAMA RRA-ERP Project 2154090
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow Municipal Authority

                                                                                                 Meeting of: 10-20-2020

                                                                                    

Title: 

title

                     Approve and authorize execution of an a agreement with Jacobs Engineering Group to provide Professional Engineering Services for the Risk and Resiliency Project (Project Number 2154090)

End

Background:

Per the America’s Water Infrastructure Act of 2018 (AWIA), the Environmental Protection Agency requires the completion of a Risk and Resiliency Assessment (RRA) to be completed by December 31, 2020 and an Emergency Response Plan (ERP) completed exactly six months later. EPA recommends the use of standard AWWA J100-10 Risk and Resilience Management of Water and Wastewater Systems to facilitate the assessments and plans. Due to the complicated nature of this assessment and response plan standard, the Utilities Department is requesting the assistance of Jacobs to complete the RRA and ERP. Jacobs has an experienced team dedicated to this task. Jacobs will evaluate the City of Broken Arrow’s water treatment and distribution system and complete the Risk and Resiliency Assessment followed by the Emergency Response Plan within the required time frame.

 

The fee for this project is $74,770.00.  Funding for the project will be from the Utilities Department Operations and Maintenance (O&M) budget, Project Number 2154090.

 

Cost:                                                                $74,770.00

Funding Source:       Utilities Department O&M Budget

Requested By:                      Charles Vokes, Utilities Director

Approved By:                      City Manager’s Office 

Attachments:                                          Agreement BAMA RRA-ERP Project 2154090

Recommendation:

recommend

Approve and authorize execution of an a agreement for Professional Engineering Services with Jacobs Engineering Group for the Risk and Resiliency Project.