LEGISLATIVE RESEARCH CENTER
File #: 20-1233    Name:
Type: Consent Item Status: Agenda Ready
File created: 9/29/2020 In control: Broken Arrow City Council
On agenda: 10/6/2020 Final action:
Title: Approval of waiver of bidding requirements set forth in Article V, Section c. and Article XIV of the City of Broken Arrow Purchasing Manual and issuance of a purchase order for the purchase of stormwater infrastructure materials from Nance Precast Concrete Products for the Washington Street Improvements from Garnett Road to Olive Avenue construction project ST1616B
Attachments: 1. 10062020 Stormwater Infrastructure ST1616B Quotation Contract, 2. 10062020 Request For Quotes For Stormwater Infrastructure ST1616B letter
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Broken Arrow City Council
Meeting of: 10-06-2020

Title:
title
Approval of waiver of bidding requirements set forth in Article V, Section c. and Article XIV of the City of Broken Arrow Purchasing Manual and issuance of a purchase order for the purchase of stormwater infrastructure materials from Nance Precast Concrete Products for the Washington Street Improvements from Garnett Road to Olive Avenue construction project ST1616B
End

Background:
The Washington Street (91st Street South) Improvements from Garnett Road (113th East Avenue) to Olive Avenue (129th East Avenue) is a 2014 Streets General Obligation Bond project. Original project number is ST1616. The bond issue calls for widening Washington Street from Garnett Road to Olive Avenue including all appurtenances. The improvements on Washington Street include approximately 1.0 mile of roadway widening from 3 to 5 lanes with asphalt pavement along with the addition of concrete curb and gutter, sidewalk/pedestrian trail, driveways, water line relocation, traffic signalization, enclosed storm sewer system, retaining wall, RCB bridge extension and RCP cross drain extension.

During the course of the project, City of Broken Arrow and H&G Paving, Inc. (Contractor) Change Ordered a reduction scope and work, with exception of the traffic signaling work and traffic control services. With this Change Order, Streets and Stormwater Department personnel are tasked with completing construction of the roadway. As part of constructing the roadway, stormwater infrastructure needs to be installed. This infrastructure consists of inlets, manholes, and pipe.

After assessing the infrastructure already installed and what structures were on site, Staff concluded that several inlets, manholes, and pipes are needed to complete the installation of the stormwater infrastructure for this project. The expected cost of the construction is below the State of Oklahoma Public Competitive Bid Act requirements, therefore, the City's...

Click here for full text