LEGISLATIVE RESEARCH CENTER
File #: 20-1181    Name:
Type: Presentations Status: Agenda Ready
File created: 9/21/2020 In control: Broken Arrow City Council
On agenda: 10/6/2020 Final action:
Title: Presentation regarding update on the Washington Street Widening Project from Garnett Road to Olive Avenue
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow City Council

Meeting of: 10-06-2020

 

Title:

title

Presentation regarding update on the Washington Street Widening Project from Garnett Road to Olive Avenue

End

 

Background:

On August 27, 2020, the City of Broken Arrow took control of the project to widen Washington Street from Garnett Road to Olive Avenue.  Progress to complete this very important project in a timely manner included utilizing City personnel from the Streets and Stormwater Department.

To keep the Council and the community informed of progress, the City Manager has requested that Staff provide the Council an update of the project.  The following presentation fulfills this request and provides the Council with an overview of progress made on this project.

 

 

Cost:                                                                $0

Funding Source:                     2014 General Obligation Bond

Requested By:                      Rocky Henkel, Streets and Stormwater Director

Approved By:                      City Manager’s Office

Attachments:                                          None

Recommendation:

recommend

Informational Only.