LEGISLATIVE RESEARCH CENTER
File #: 20-499    Name:
Type: Consent Item Status: Agenda Ready
File created: 5/11/2020 In control: Broken Arrow Municipal Authority
On agenda: 5/19/2020 Final action:
Title: Approval of and authorization to execute Amendment No. 1 to Professional Services Agreement with Professional Engineering Consultants, P.A. for County Line Trunk Sewer - Phase 1 (Project No. S.1609)
Attachments: 1. Amendment No. 1
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow Municipal Authority

Meeting of: 05-19-2020

 

Title:

title

Approval of and authorization to execute Amendment No. 1 to Professional Services Agreement with Professional Engineering Consultants, P.A. for County Line Trunk Sewer - Phase 1 (Project No. S.1609)

End

 

Background:

The County Line Trunk Sewer - Phase 1 project is currently being constructed.  The original contract with Professional Engineering Consultants, P.A. (PEC) provided for design work for the project and some assistance during construction services. 

This Amendment requires CONSULTANT to provide modifications to plans due to field changes, additional services during construction due to changes in the field, review of Contractor Requests for Information and response to same, and coordination with Contractor and Owner Personnel for field resolution of issues.  The negotiated amount of this amendment with PEC is $37,800.00.

 

Cost:                                                                $37,800.00

Funding Source:                     Oklahoma Water Resources Board Loan

Requested By:                      Ethan J.L. Edwards, P.E., Director of Engineering & Construction

Approved By:                      City Manager’s Office

Attachments:                                          Amendment No. 1 to Professional Services Agreement

 

Recommendation:

recommend

Approve and authorize execution of Amendment No.1 to Professional Services Agreement with Professional Engineering Consultants, P.A. for County Line Trunk Sewer - Phase 1 (Project No. S.1609)