Acknowledgement of submittal of the Broken Arrow Municipal Authority’s Wastewater Discharge Monitoring Report for the month of February 2020
End
Background:
In an effort to provide the Authority and the Public more information with respect to our community’s wastewater collection and treatment at the City’s Lynn Lane Wastewater Treatment Plant, the Utilities Department staff is attaching a copy of the February 2020 Oklahoma Department of Environmental Quality (ODEQ) Discharge Monitoring Report (DMR) submitted to ODEQ on March 13, 2020.
Over the course of the month of February 2020, the total wastewater collected, treated and discharged is 194.384 million gallons (MG). The average flow was 6.577 MG.
This report will be updated on a monthly basis. Staff recommends the Authority acknowledge submittal of the Report.
Cost: None
Funding Source: None
Requested By: Charles Vokes, Utilities Director
Approved By: City Manager’s Office
Attachments: February Discharge Monitoring Report
February Monthly Operational Report
Recommendation:
recommend
Acknowledge submittal of the February 2020 Monthly Discharge Monitoring Report