Broken Arrow Municipal Authority
Meeting of: 09-17-2019
Title:
title
Approval of and authorization to execute an Amendment to the Professional Consultant Agreement with Tetra Tech, Inc. for Lynn Lane Secondary Clarifier Rehabilitation (Project No. 165422)
End
Background:
Tetra Tech, Inc. was hired in 2015 to design Rehabilitation of the Secondary Clarifier at Lynn Lane Wastewater Treatment Plat (LLWWTP). This rehab design also included a new nonpotable water design that would be used for certain purposes at the plant. This project was put out to bid in June of 2019 and the bids were opened on August 6th 2019. The initial contract with Tetra Tech, Inc. only covered assistance through the bidding process. Due to the complexity of this project and the number of expected submittals an Amendment to their contract for Construction Services was deemed to be appropriate.
The Engineering and Construction Department negotiated an Amendment to the Professional Consultant Agreement with Tetra Tech, Inc.to provide Construction services. The negotiated amount is $116,500.00.
Cost: $116,500.00
Funding Source: OWRB Loan ORF-17-0005-CW
Requested By: Kenneth D. Schwab P.E., CFM, Assistant City Manager- Operations
Approved By: City Manager’s Office
Attachments: Professional Consultant Agreement Amendment with Tetra Tech, Inc.
Recommendation:
recommend
Approve and authorize execution of an Amendment to the Professional Consultant Agreement with Tetra Tech, Inc. for Lynn Lane Secondary Clarifier Rehabilitation (Project No. 165422)
end