Title: Approval of and authorization to execute Change Order CO2 for Construction Contract 171703; Tiger Hill Soldier Pile Retaining Wall
Attachments: 1. Tiger Hill Solder Pile Retaining Wall - Change Order #2
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Broken Arrow City Council
Meeting of: 5-21-2019

Title:
title
Approval of and authorization to execute Change Order CO2 for Construction Contract 171703; Tiger Hill Soldier Pile Retaining Wall
End

Background:
The Tiger Hill Soldier Pile Retaining Wall project serves as a second retaining wall on the tiger hill site at the southeast corner of 9th Street and Kenosha, ultimately serving as a supplemental structural support for the existing retaining wall. This retaining wall also acts as a mechanism to facilitate the lowering of the grade of the adjacent project. The City advertised the construction documents on September 25, 2018 and October 2, 2018, and opened bids on October 16, 2018. The contract was awarded to the low bidder, Stronghand LLC. at a contract cost of $1,498,681.24. Notice to proceed was issued to the contractor on January 7, 2019.

This Change Order #2 addresses the following additions to the contract:
CO2-1
As reflected in RFI #4 for the Tiger Hill Soldier Pile Wall project, the existing storm sewer on the east side of the existing retaining wall is in conflict with the proposed soldier pile wall drilled pile. The existing storm sewer line shall be relocated around the conflicting dilled pile to the south with appropriate bends from the proposed new storm manhole around and back to the existing alignment of the storm sewer. The below costs summarize a complete in place product and all applicable mark ups are included.

Contract Time Adjustments:
- None requested

The additional cost associated with these changes is as follows:
Previous Change Orders: $75,900.00
This Change Order: $4,725.51
Total Cost of Change Orders: $80,625.51
Original Contract Amount: $1,498,681.24
Revised Contract Amount: $1,579,306.75
Percent Change in Contract: 5.38%
Applicable to Comp. Bid Act: 5.38%


Cost: $4,725.51
Funding Source: Sales Tax Capital Improvements (STCI)
Requested By: Alex Mills, PE CFM, Engineering and Construction Director