Title: Approval of and authorization of Final Acceptance for the public improvements at Aspen Crossing Phase I located at the North East corner of Aspen Avenue and Jasper
Attachments: 1. Infrastructure Inventory

Broken Arrow City Council

Meeting of: 05-07-2019

 

Title:

title

Approval of and authorization of Final Acceptance for the public improvements at Aspen Crossing Phase I located at the North East corner of Aspen Avenue and Jasper

End

 

Background:

Ira M. Green has completed the construction for the Aspen Crossing Phase I.  The required improvements are in accordance with approved construction plans and appropriate construction documents. These improvements have been constructed under the supervision of the City of Broken Arrow, Department of Engineering and Construction.

Said Improvements are the following: (1) Water; (2) Sanitary Sewer.

The owner desires to donate the public improvements identified above to the City.  These improvements have an approximate value of $238,062.75.

 

Cost:                                                                $0

Funding Source:                     N/A

Requested By:                      Alex Mills, P.E., Engineering and Construction, Director

Approved By:                      City Manager Office

Attachments:                                          Detailed Assessment Breakdown

Recommendation:

recommend

Approve and authorize Final Acceptance of the Public Improvements at Aspen Creek Crossing Phase I:   Water; Sanitary Sewer.

end