Broken Arrow Municipal Authority
Meeting of: 05-07-2019
Title:
title
Acknowledgement of submittal of the Broken Arrow Municipal Authority’s Wastewater Discharge Monitoring Report for the month of March 2019
End
Background:
In an effort to provide the Authority and the Public more information with respect to our community’s wastewater collection and treatment at the City’s Lynn Lane Wastewater Treatment Plant, the Utilities Department staff is attaching a copy of the March 2019 Oklahoma Department of Environmental Quality (ODEQ) Discharge Monitoring Report (DMR) submitted to ODEQ on April 15, 2019.
Over the course of the month of March 2019, the total wastewater collected, treated and discharged is 155.30 million gallons (MG). The average flow was 3.296 MG.
This report will be updated on a monthly basis. Staff recommends the Authority acknowledge submittal of the Report.
Cost: None
Funding Source: None
Requested By: Charles Vokes, Utilities Director
Approved By: Michael L. Spurgeon, City Manager
Attachments: March Discharge Monitoring Report
March Monthly Operational Report
Recommendation:
recommend
Acknowledge submittal of the March 2019 Monthly Discharge Monitoring Report.
end