File #: 19-187    Name:
Type: Consent Item Status: Agenda Ready
File created: 1/23/2019 In control: Broken Arrow City Council
On agenda: 2/5/2019 Final action:
Title: Acceptance of a Utility Easement consisting of 0.08 acres and 0.39 acres of Temporary Construction Easement from the W. Paul Sommer Revocable Trust, on property located at the northwest corner of S 23rd and the Creek Turnpike, located in part of the Southeast Quarter of Section 36, Township 18 North, Range 14 East, Tulsa County, State of Oklahoma, and authorization for payment in the amount of $14,600.00 for the County Line Trunk Sewer Replacement, Parcel 13.0, 13.1 (Project No. S.1609)
Attachments: 1. Acceptance Letter, 2. Utility Easement, 3. Temporary Construction Easement
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Broken Arrow City Council
Meeting of: 2-5-2019

Title:
title
Acceptance of a Utility Easement consisting of 0.08 acres and 0.39 acres of Temporary Construction Easement from the W. Paul Sommer Revocable Trust, on property located at the northwest corner of S 23rd and the Creek Turnpike, located in part of the Southeast Quarter of Section 36, Township 18 North, Range 14 East, Tulsa County, State of Oklahoma, and authorization for payment in the amount of $14,600.00 for the County Line Trunk Sewer Replacement, Parcel 13.0, 13.1 (Project No. S.1609)
End
Background:
The attached Utility Easement and Temporary Construction Easement is being conveyed to the City of Broken Arrow from W. Paul Sommer Revocable Trust, the owner. Parcel 13.0 consists of 0.08 acres of Utility Easement and 0.39 acres of Temporary Construction Easement for the County Line Trunk Sewer Replacement, located in the Southeast Quarter of Section 36, Township 18 North, Range 14 East, Tulsa County, State of Oklahoma. The Sommer Trust has accepted the following offer, made subject to City Council approval:

Utility Easement: 3,600.71 SQUARE FEET (SF) @ $2.40 SF x 75% = $6,481.28
Temporary Construction Easement: 13.1 Rental Period until 12/31/2020
16,889.26 SF @ $2.40 SF x 20% = $8,106.84
Total Just Compensation Amount (Rounded) = $14,600.00

A copy of the signed acceptance of the City's offer is attached, as is the Utility Easement and Temporary Construction Easement. Payment of the compensation amount is on the February 5, 2019 City Council Claims List.

Cost: $14,600.00
Funding Source: OWRB FAP Loan
Requested By: Alex Mills, P.E., CFM, Engineering & Construction Director
Approved By: Michael L. Spurgeon, City Manager
Attachments: Acceptance Letter
Utility Easement
Temporary Construction Easement