Broken Arrow City Council
Meeting of: 2-05-2019
Title:
title
Award the lowest responsible bid to Cherokee Pride Construction and approve and authorize execution of a construction contract for the Aspen Pond - West Boston Court Drainage improvements (SW1918)
End
Background:
Stormwater was ponding at West Boston Court between South Narcissus Court and South Narcissus rendering the street impassible during storm events. The City is responsible for maintenance and repair of city owned streets and storm sewers. City of Broken Arrow Engineering and Construction Department personnel designed and produced construction plans for bid. The project consists of constructing two new inlets, two new manholes as well as 15” and 30” diameter drainage pipes to improve drainage in West Boston Court within the Aspen Pond Subdivision.
The project was advertised for bid on January 7,2019. Bids were opened on January 29, 2019 and 13 bids were received. All bids were responsive except one and the lowest responsible bid was from Cherokee Pride Construction for $78,704.00 The engineer’s estimate was $89,275.50 and the Certified Bid Tabulation is attached.
Cost: $78,704.00
Funding Source: 2018 General Obligation Bond Program
Requested By: Alex Mills, P.E., Engineering and Construction Director
Approved By: Michael L. Spurgeon, City Manager
Attachments: Certified Bid Tabulation
Recommendation:
recommend
Award the lowest responsible bid to Cherokee Pride Construction and approve and authorize execution of a construction contract for the Aspen Pond - West Boston Court Drainage Improvements (SW1918)
end