File #: 18-1386    Name:
Type: Consent Item Status: Passed
File created: 11/27/2018 In control: Broken Arrow Municipal Authority
On agenda: 12/4/2018 Final action: 12/4/2018
Title: Approval of and authorization to execute Change Order CO1 for Construction Contract 175436; Verdigris River Water Treatment Plant Pretreatment Basin Expansion
Attachments: 1. 175436 Change Order #1
Broken Arrow Municipal Authority
Meeting of: 12-4-2018

Title:
title
Approval of and authorization to execute Change Order CO1 for Construction Contract 175436; Verdigris River Water Treatment Plant Pretreatment Basin Expansion
End
Background:
Over the past three years of operation of the Verdigris River Water Treatment Plant, the raw water quality during the warm weather months has created challenges with producing settled water quality within turbidity goals for optimum membrane filtration operation. The purpose of this project will provide improvements to the pretreatment basin. The project consists of construction of two (2) rapid mix basins, two (2) train flocculation basins with plate settlers, a residual collection and pumping system and modifications to the chemical feed storage and pumping system and all appurtenances. The project was advertised for bid on July 23, 2018. Bids were opened on August 14, 2018, with the lowest responsible bidder being Walters-Morgan Construction, Inc., with a Base Bid of $6,702,000.00, Alternate A of $74,000, Alternate B of $57,000 for a Total Lump Sum Bid of $6,833,000. A Notice to Proceed was issued to the contractor on August 8th, 2018.

This Change Order #1 addresses the following additions to the contract:

Total Number of Days Added by this Change Order:
- None requested due to these changes

CO1-1 - Specifications for the project currently place the construction materials testing obligations throughout the contract as the responsibility of the owner to provide as noted within section 03 05 05 Paragraph 1.2A. This change order is to modify this requirement to place the construction materials testing obligations solely on the contractor. This is to include all third party materials testing required noted within the plans. The below costs are inclusive of all associated labor, materials, and markups as noted within the proposal.

CO1-2 - As related to RFI #005, a conflicting 16" SW Line shall be removed to ...