Acknowledgement of submittal of the Broken Arrow Municipal Authority’s Wastewater Discharge Monitoring Report for the month of October 2018
End
Background:
In an effort to provide the Authority and the Public more information with respect to our community’s wastewater collection and treatment at the city’s Lynn Lane Wastewater Treatment Plant, the Utilities Department staff is attaching a copy of the October 2018 Oklahoma Department of Environmental Quality (ODEQ) Discharge Monitoring Report (DMR) submitted to ODEQ on November 15, 2018.
Over the course of the month of October 2018, the total wastewater collected, treated and discharged is 137.79 million gallons (MG). The average flow was 3.160 MG.
This report will be updated on a monthly basis. Staff recommends the Authority acknowledge submittal of the Report.
Cost: None
Funding Source: None
Requested By: Charles Vokes, Utilities Director
Approved By: Michael L. Spurgeon, City Manager
Attachments: October Discharge Monitoring Report
October Monthly Operational Report
Recommendation:
recommend
Acknowledge submittal of the Monthly Discharge Monitoring Report.