LEGISLATIVE RESEARCH CENTER
File #: 18-1339    Name:
Type: Consent Item Status: Passed
File created: 11/14/2018 In control: Broken Arrow City Council
On agenda: 11/20/2018 Final action: 11/20/2018
Title: Notification of Change Orders or Work Orders with a value of less than $25,000 on Public Contracts
Attachments: 1. CItywide Striping Plan - Change Order #1

    Broken Arrow City Council

                                                                                                       Meeting of: 11-20-18

                                                                                    

Title: 

title

                     Notification of Change Orders or Work Orders with a value of less than $25,000 on Public Contracts 

End

 

Background:

The City Manager or his designated representative has the authority to execute Contracts, Change Orders, and Work Orders with a total increase in value of less than $25,000.  Attached are the Change Orders that have been executed since the last City Council meeting.  No action is required.  This item is for information only.

 

Cost:                                                                $(6,279.88)

Funding Source:        2019 Street Sales Tax                               

Requested By:                      Alex Mills, P.E., Engineering and Construction Director

                                   

Approved By:                      Michael L. Spurgeon, City Manager 

 

Attachments:                                          CHANGE ORDERS: 
Citywide Striping Plan, Project Number ST1803, Direct Traffic Control, Inc.;
Change Order CO-1, $(6,279.88).

Recommendation:

recommend

No action required.

end