Presentation regarding the road closures for Evans Road Railroad Crossing in association with Union Pacific Railroad Rehabilitating the Crossing
End
Background:
The Union Pacific (UP) Railroad plans to rehabilitate the Evans Road crossing on September 19, 2018. The crossing will be closed from 8:00 AM to 5:00 PM. The road closure will take effect from the intersection of the Evans Road and SH-51 to the south side of the UP Railroad. A detour route will be signed to take through traffic along 101st Street to 241st East Avenue to SH-51. It will just inconvenience the traveling public for one day.
The road closure will allow the contractor to complete the rehabilitation of the Railroad crossing in one day.
Traffic signs will be placed in roadway prior to closure advising the traveling public of the pending detour.
Cost: $0
Funding Source: N/A
Requested By: Alex Mills, P.E., Director of Engineering and Construction
Approved By: Michael L. Spurgeon, City Manager
Attachments: Detour Plan by Road Safety Traffic
Recommendation:
recommend
No action required