Approval of and authorization to execute 2017 CDBG Resolution Contract/Agreement Renewal with Tulsa County from July 1, 2018 to June 30, 2019 for 4th Street Rehabilitation Project (Project No ST1804)
End
Background:
In October 2017, a Community Development Block Grant agreement for the 4th Street Rehabilitation was signed by Tulsa County and the City of Broken Arrow. The agreement had a provision that an extension could be granted if the grant was not fully spent by June 30, 2018. This resolution with Tulsa County is to extend the deadline to June 30, 2019, give the contractor time to complete the project.
Cost: $0
Funding Source: N/A
Requested By: Alex Mills, P.E., CFM, Director of Engineering and Construction
Approved By: Michael L. Spurgeon, City Manager
Attachments: Contract/Agreement Renewal Resolution.
Recommendation:
recommend
Approve and authorize execution of Resolution Contract/Agreement Renewal for 4th Street Rehabilitation Project.