LEGISLATIVE RESEARCH CENTER
File #: 18-172    Name:
Type: Consent Item Status: Agenda Ready
File created: 1/10/2018 In control: Broken Arrow Municipal Authority
On agenda: 1/16/2018 Final action:
Title: Approval of and authorization to execute Amendment No. 1 to an Agreement for Professional Consultant Services with Tetra Tech, Inc., for design of Digester Rehabilitation at the Lynn Lane Wastewater Treatment Plant
Attachments: 1. 170116 Amend No 1
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow Municipal Authority

                                                                                               Meeting of: 1-16-2018

                                                                                    

To:                     Chairman and Authority Members

From:                     Engineering and Construction Department

Title: 

title

                     Approval of and authorization to execute Amendment No. 1 to an Agreement for Professional Consultant Services with Tetra Tech, Inc., for design of Digester Rehabilitation at the Lynn Lane Wastewater Treatment Plant 

End

Background:

Digester Rehabilitation at Lynn Lane Wastewater Treatment Plant (LLWWTP) is a project recommended from the Sludge Digestion Evaluation contract performed by Tetra Tech.  The project consists of cleaning debris from the digesters, rehabilitating the aerations piping and replacing the fine bubble diffusers with coarse bubble diffusers. 

 

The construction project has bid and been awarded this contract Amendment is for engineering assistance during construction and at the conclusion of the construction contract the preparation of record drawings and the preparation of a sludge process operations manual to guide staff in operations of the digesters.

 

Funding for this Amendment is from the FAP construction loan (FAP-17-004-L).

 


Cost:                                                                $35,000.00

Prepared By:                                           Alex M. Mills, P.E., CFM, Engineering and Construction Director

Reviewed By:                                          Utilities Department
            Finance Department
            Legal Department
            Assistant City Manager                                  

 

Approved By:                      Michael L. Spurgeon, City Manager
                                 

Attachments:                                          Professional Consultant Agreement Amendment No. 1

Recommendation:

Approve and authorize execution of Amendment No. 1 to a Professional Consultant Agreement with Tetra Tech, Inc., for Digester Rehabilitation at the Lynn Lane Wastewater Treatment Plant.