Title: Approval of and authorization to execute a Professional Consultant Agreement with R.L. Shears Company, P.C., for Detailed Design and Construction Bid Documents of Downtown Main Street Streetscapes, Phase V
Attachments: 1. 170810 Agreement RL Shears-Streetscapes V-Signed by Legal.pdf

Broken Arrow City Council

                                                                                               Meeting of: 08-15-2017

                                                                                    

To:                     Mayor and City Council

From:                     Engineering and Construction Department

Title: 

title

                     Approval of and authorization to execute a Professional Consultant Agreement with R.L. Shears Company, P.C., for Detailed Design and Construction Bid Documents of Downtown Main Street Streetscapes, Phase V

End

Background:

Phase V of the Downtown Main Street Streetscapes is a Sales Tax Capital Improvements (STCI) project, with additional Vision 2025 surplus funding tentatively approved by Tulsa County.  The project encompasses Main Street from Detroit Street to Elgin Street.  RL Shears Company, P.C. has submitted a proposal for producing the detailed design and construction bid documents for the Phase V project, and the Professional Consultant Agreement has been prepared (attached).  A cost of $155,770.00 is proposed for the design and preparation of construction plans and specifications, as well as Bidding and Construction Phase services.  Staff recommends award of the Professional Consultant Agreement with RL Shears Company, P.C. 

 

Funding will be from Sales Tax Capital Improvements with reimbursement from Vision 2025 Surplus Funds. 


Cost:                                                                $155,770.00

Prepared By:                                           Alex Mills, P.E., Engineering and Construction Director

Reviewed By:                                          Finance Department
                                    Legal Department
                                   Assistant City Manager                              

Approved By:                      Michael L. Spurgeon, City Manager
                                   

Attachments:                                          Professional Consultant Agreement for Detailed Design and Construction Bid Documents

Recommendation:

Approve and authorize execution of the Professional Consultant Agreement with R.L. Shears Company, P.C., for detailed design and construction bid documents for Downtown Main Street Streetscapes Phase V