LEGISLATIVE RESEARCH CENTER
File #: 17-2531    Name:
Type: General Business Status: Passed
File created: 8/7/2017 In control: Broken Arrow City Council
On agenda: 8/15/2017 Final action: 8/15/2017
Title: Consideration, discussion, and possible award of the lowest responsible bid to Cherokee Pride Construction, and approve and authorize execution of a construction contract for Rose West Dog Park and Restroom (Project No. 126038)
Attachments: 1. Certified Bid Tab.pdf

Broken Arrow City Council

                                                                                               Meeting of: 08-15-17

                                                               

To:                     Mayor and City Council

From:                     Engineering and Construction Department

Title: 

title

                     Consideration, discussion, and possible award of the lowest responsible bid to Cherokee Pride Construction, and approve and authorize execution of a construction contract for Rose West Dog Park and Restroom (Project No. 126038)

End

Background:

The Rose West Dog Park and Restroom is a 2014 General Obligation Bond Project.  The purpose of the project is to construct the Rose West Dog park located on West New Orleans Street (101st Street South) east of Garnett, including facilities for a dog park, a trail head restroom and expansion of the parking area.  The bid documents included a Base Bid for the park and the restroom building. The project was advertised for bids on June 28 and July 5, 2017.  Bids were opened on August 1, 2017.  Eight (8) bids were received.  The low bidder was Cherokee Pride Construction with a bid of $532,700.50.  The certified bid tabulation is attached.  Staff recommends award of the Base Bid for Rose West Dog Park and Restroom to Cherokee Pride Construction, in the amount of $532,700.50.

 

Funds for the work are available in the 2014 General Obligation Bond.

 

Cost:                                                                $532,700.50

Prepared By:                                           Alex M. Mills, P.E., CFM, Engineering and Construction Director

Reviewed By:                                          Parks & Recreation Department
                                    Finance Department
                                    Assistant City Manager - Operations

 

Approved By:                      Michael L. Spurgeon, City Manager
                                  

Attachments:                                          Certified Bid Tabulation

Recommendation:

Award the lowest responsible bid to Cherokee Pride Construction and approve and authorize execution of a construction contract for Rose West Dog Park and Restroom