Title: Award the lowest responsible bid to Cook Consulting, LLC, and approve and authorize execution of a construction contract for 4-Ton Bridge Rehabilitation (Project No. ST1303)
Attachments: 1. Certified Bid Tab.pdf

Broken Arrow City Council

                                                                                               Meeting of: 08-01-17

                                                                                    

To:                     Mayor and City Council

From:                     Engineering and Construction Department

Title: 

title

                     Award the lowest responsible bid to Cook Consulting, LLC, and approve and authorize execution of a construction contract for 4-Ton Bridge Rehabilitation (Project No. ST1303)

End

Background:

The bridge over Broken Arrow Creek on 23rd Street just south of Washington Street has been load-posted with a weight limit of 4 tons for several years.  The bridge is an old County bridge with steel girders and a wood deck under an asphaltic concrete surface.  Biannual bridge inspections have determined that the bridge is a safety hazard, and the load-posting has caused inconveniences to motorists and caused school buses and other heavy traffic to be rerouted around it. A professional consultant agreement with NEO Design, Inc., was negotiated in March 2017, and the engineer produced a design in May which was used as a basis for bid documents.

 

The project was advertised for bids on June 28 and July 5, 2017.  Bids were opened on July 25, 2017 and three (3) bids were received.  All bids were responsive.  The Certified Bid Tabulation is attached.  The lowest responsible bidder was Cook Consulting, LLC, with a bid of $18,500.00.  The engineer’s estimate was $20,000.00.  Staff recommends awarding the Bid in the amount of $18,500.00 to Cook Consulting, LLC.

 

Funding for the improvements will be from Sales Tax Capital Improvements (STCI) funds.


Cost:                                                                $18,500.00

Prepared By:                                           Alex M. Mills, P.E., Director of Engineering and Construction

Reviewed By:                                          Engineering and Construction Department
                                    Streets & Stormwater Department
                                    Finance Department                                    
                                    Assistant City Manager - Operations

                                    Legal Department

Approved By:                      Michael L. Spurgeon, City Manager                                   

Attachments:                                          Certified Bid Tabulation

Recommendation:

Award the lowest responsible bid to Cook Consulting, LLC, and approve and authorize execution of a construction contract for 4-Ton Bridge Rehabilitation