LEGISLATIVE RESEARCH CENTER
File #: 17-2474    Name:
Type: Consent Item Status: Agenda Ready
File created: 7/24/2017 In control: Broken Arrow City Council
On agenda: 8/1/2017 Final action:
Title: Award the lowest responsible bid to Traffic & Lighting Systems, LLC, and approve and authorize execution of a construction contract for Kenosha and 79th Street Traffic Signal (Project No. 175115)
Attachments: 1. Certified Bid Tabulation.pdf

Broken Arrow City Council

                                                                                               Meeting of: 08-01-17

                                                                                    

To:                     Mayor and City Council

From:                     Engineering and Construction Department

Title: 

title

                     Award the lowest responsible bid to Traffic & Lighting Systems, LLC, and approve and authorize execution of a construction contract for Kenosha and 79th Street Traffic Signal (Project No. 175115)

End

Background:

This project is to install a new traffic signal at a 4-way arterial intersection currently controlled by north-southbound stop signs.  79th Street (Midway Road) is a 2-lane street and Kenosha is a 4-lane street.  Included is the signal controller cabinet, 8-phase controller, mast arm poles, and pull boxes.

 

The project was advertised for bids on June 23 and June 30, 2017.  Bids were opened on July 18, 2017 and three (3) bids were received.  All bids were responsive.  The Certified Bid Tabulation is attached.  The lowest responsible bidder was Traffic & Lighting Systems, LLC, with a bid of $170,023.26.  The engineer’s estimate was $173,746.39.

 

Staff recommends awarding the Bid in the amount of $170,023.26 to Traffic & Lighting Systems, LLC.

 

Funding for the improvements will be from Fund 42, Street Light Fund.


Cost:                                                                $170,023.26

Prepared By:                                           Alex M. Mills, P.E., Engineering and Construction Director

Reviewed By:                                          Engineering and Construction Department
                                    Finance Department
                                    Legal Department
                                    Assistant City Manager - Operations

Approved By:                      Michael L. Spurgeon, City Manager                                   

Attachments:                                          Certified Bid Tabulation

Recommendation:

Award the lowest responsible base bid to Traffic & Lighting Systems, LLC, and approve and authorize execution of a construction contract for Kenosha and 79th Street Traffic Signal Trail.