Title: Ratification of a Construction Services Contract between the Regional Metropolitan Utility Authority (RMUA) and Southeast Tulsa Construction, Inc., for services associated with the replacement of the Operations building roof at the Haikey Creek Waste Water Treatment Plant (base bid plus additive alternate no. 1) and authorize the Authority to pay its representative portion (approximately $81,782.42)
Attachments: 1. RMUA HCWWTP roof
Broken Arrow Municipal Authority
Meeting of: 05-02-2017

To: Chairman and Authority Members
From: Utilities Department
Title: title
Ratification of a Construction Services Contract between the Regional Metropolitan Utility Authority (RMUA) and Southeast Tulsa Construction, Inc., for services associated with the replacement of the Operations building roof at the Haikey Creek Waste Water Treatment Plant (base bid plus additive alternate no. 1) and authorize the Authority to pay its representative portion (approximately $81,782.42)
end
Background:
The Haikey Creek Waste Water Treatment Plant is jointly utilized by the Broken Arrow Municipal Authority (BAMA) and the Tulsa Municipal Utility Authority (TMUA). Pursuant to an agreement with the Regional Metropolitan Utility Authority, the plant is operated by the City of Tulsa. As part of the Fiscal Year 2017 Operations and Maintenance Budget, plant staff had identified the roof at the operations building is in need of replacement. The roof is leaking at several locations and has damaged ceiling tiles. The funds identified for the project is
$82,000.00. Project Number 175428

In December of 2015, the City of Tulsa had engaged the services of a roof consultant to inspect all the roofs at the Haikey Creek Plant and presented a report on the findings of the inspection. The "Roof Consultants," reported the Operations Building roof had sustained hail damage in 2011 and temporary repairs had been made which were failing and the roof needs to be replaced.

The City of Tulsa solicited bid using the bid specifications prepared by a consultant engaged by the City of Tulsa. Three bid proposals were received. City of Tulsa operations staff reviewed the bids received and recommended awarding the project to Southeast Tulsa Construction, Inc., in the amount of $ 163,564.87. BAMA's contribution is $81,782.42. Funding is available in the Waste Water Treatment C...