Title: Approval of and authorization to execute Resolution No. 1016, a Resolution authorizing the acceptance of a General Warranty Deed, Utility Easement, and Temporary Construction Easement for Parcel 23, which consists of 0.121 acres of Permanent Right-of-Way and .133 acres of Easement for 9th Street Widening Elgin to El Paso, being part of the NE 1/4 of the SE 1/4 of Section 11, Township 18 North, Range 14 East, Tulsa County, from PACCAR, Inc., and authorization of payment in the amount of $20,500.00 to PACCAR, Inc. for the 9th Street Widening from Elgin to El Paso Project (Project No. ST1210)
Attachments: 1. 170502 PACCAR Resolution 1016, 2. 170502 PACCAR CC Docs Revised

Broken Arrow City Council

                                                                                               Meeting of: 05/02/17

                                                                                    

To:                     Mayor and City Council

From:                     Engineering and Construction Department

Title: 

title

                     Approval of and authorization to execute Resolution No. 1016, a Resolution authorizing the acceptance of a General Warranty Deed, Utility Easement, and Temporary Construction Easement for Parcel 23, which consists of 0.121 acres of Permanent Right-of-Way and .133 acres of Easement for 9th Street Widening Elgin to El Paso, being part of the NE 1/4 of the SE 1/4 of Section 11, Township 18 North, Range 14 East, Tulsa County, from PACCAR, Inc., and authorization of payment in the amount of $20,500.00 to PACCAR, Inc. for the 9th Street Widening from Elgin to El Paso Project (Project No. ST1210)

End

Background:

The attached General Warranty Deed, Utility Easement, and Temporary Construction Easement are conveyed to the City of Broken Arrow by PACCAR, Inc. The City’s Right-of-Way Agent has negotiated payment of $22,500.00 with PACCAR, Inc., the property owner of Parcel 23. The General Warranty Deed, Utility Easement, and Temporary Construction Easement are attached.


Cost:                                                                $20,500.00

Prepared By:                                           Alex M. Mills, P.E., CFM, Engineering and Construction Director

Reviewed By:                                          Finance Department
                                   City Attorney
                                   Assistant City Manager - Operations

 

Approved By:                      Michael L. Spurgeon, City Manager
                                   

Attachments:                                          Resolution 1016
                                    Offer Letter
                                    General Warranty Deed
                                    Utility Easement
                                    Temporary Construction Easement

Recommendation:

Accept Resolution No. 1016 and authorize its execution