File #: 17-1968    Name:
Type: Consent Item Status: Passed
File created: 3/14/2017 In control: Broken Arrow City Council
On agenda: 3/21/2017 Final action: 3/21/2017
Title: Approval of and authorization to execute Change Order C05-Final for Construction Contract ST1307 with Magnum Construction; Dallas Street Improvements
Attachments: 1. ST1307 Dallas Street Change Order - Final

Broken Arrow City Council

                                                                                               Meeting of: 3-21-17

                                                                                    

To:                     Mayor and City Council

From:                     Engineering and Construction Department

Title: 

title

                     Approval of and authorization to execute Change Order C05-Final for Construction Contract ST1307 with Magnum Construction; Dallas Street Improvements

End

Background:

The Dallas Street Improvements from Elm Place to the alley east of Ash Avenue is a Downtown Street Improvements project approved in the 2008 and 2011 Streets GO Bond election.  The improvements consist of repaving the existing 2-lane street, addition or replacement of curbs and gutters, storm drains, and sidewalks, and replacement of the existing 2- and 4-inch water lines with an 8-inch PVC line. The project was advertised for bids on June 9 and June 16, 2014, and bids were opened on July 15, 2014.  Magnum Construction, Inc., was awarded the contract in the amount of $816,060.00. Notice to proceed on the contract was issued August 25, 2014.

 

This Change Order #5-Final addresses the following additions to the contract:

 

1.  Total Number of Days Added by this Change Order:                                                                                                         

- Additional time due to project delays and remobilization for the Rail Road ROW work in 2017, contract day count shall be amended to include an additional 720 days revising the contract calendar time to 921 days. 

                                                                                                         

2.                     Reconciling Changes: Due to site conditions varying from design parameters, field

    adjustments of the plan quantities by the city contract administrator was authorized.

    These changes in quantities are summarized on the attached "Project Final Quantities

    Report". The listed change order cost is to adjust the original contract value to the

    reflected installed contract value.                     

                                                               

                                          

The additional cost associated with these changes is as follows:

Previous Change Orders:                                          $70,612.00

This Change Order:                                                               $92,562.27

Total Cost of Change Orders:                                          $163,174.27

Original Contract Amount:                                          $816,060.00

Revised Contract Amount:                                          $979,234.27

Percent Change in Contract:                                          20.00%

Applicable to Comp. Bid Act:                     8.65%

 

Funding for the change order will come from the 2011 General Obligation Bond.

 

 

 


Cost:                                                                $92,562.27

Prepared By:                                           Alex Mills, P.E, Director of Engineering and Construction

Reviewed By:                                          Engineering and Construction Department                                  
                                    Finance Department
                                    Assistant City Manager - Operations
                                    Legal Department
                                 

Approved By:                      Michael L. Spurgeon, City Manager
                             

Attachments:                                          ST1307 Change Order #05 & Final Quantities Report

Recommendation:

Staff recommends approving Change Order #05 for the Dallas Street Improvements Project.