LEGISLATIVE RESEARCH CENTER
File #: 17-1890    Name:
Type: General Business Status: Passed
File created: 2/21/2017 In control: Broken Arrow City Council
On agenda: 3/7/2017 Final action: 3/7/2017
Title: Consideration, discussion, and possible award of the lowest responsible bid plus Alternates 1 and 2 to Becco Contractors, Inc, and authorize execution of a construction contract for Kenosha: Garnett to Aspen Mill and Overlay (Project No. ST1713)
Attachments: 1. 170222 Bid Tab Certified Kenosha Garnett-Aspen Mill and Overlay

Broken Arrow City Council

                                                                                               Meeting of: 03-07-17

                                                                                    

To:                     Mayor and City Council

From:                     Engineering and Construction Department

Title: 

title

                     Consideration, discussion, and possible award of the lowest responsible bid plus Alternates 1 and 2 to Becco Contractors, Inc, and authorize execution of a construction contract for Kenosha: Garnett to Aspen Mill and Overlay (Project No. ST1713)

End

Background:

The Kenosha: Garnett to Aspen Mill and Overlay is a 2014 Streets General Obligation Bond project.  The project was divided into a Base bid and two Additive Alternates to ensure that funding was adequate to complete the contract.  The extents of the Base Bid were from Yellowwood Avenue to Aspen Avenue, excluding the Olive intersection, which is planned to be rebuilt as part of the Olive, Kenosha to Albany project.  Alternate 1 extends from Yellowood Avenue to Cypress Ave., and Alternate 2 extends from Cypress Avenue to 1/8 mile east of Garnett Road. 

 

The project was advertised for bids on January 31 and February 7, 2017, and bids were opened on February 21, 2017.  Five (5) bids were received.  The low bidder was Becco Contractors, Inc., with a proposal of $616,038.70 for the Base Bid, $106,644.25 for Alternate 1, and $103,275.60 for Alternate 2, for a total of $825,958.55.  The engineer’s estimate was $843,210.00 for the Base Bid, $148,143.50 for Additive Alternate No. 1, and $136,310.00 for Alternate No. 2, for a total of $1,127,663.50.  The certified bid tabulation is attached.  Staff recommends award of the Kenosha: Garnett to Aspen Mill and Overlay Base Bid and Alternates 1 and 2 to Becco Contractors, Inc., in the amount of $825,958.55.

 

Funds for the work are available in 2014 Streets GO Bond.

 

Cost:                                                                $825,958.55

Prepared By:                                           Alex M. Mills, P.E., CFM, Engineering and Construction Director

Reviewed By:                                          Streets and Stormwater Department
                                    Finance Department
                                    City Attorney
                                    Assistant City Manager - Operations

 

Approved By:                      Michael L. Spurgeon, City Manager
                                  

Attachments:                                          Certified Bid Tabulation

Recommendation:

Award the lowest responsible bid to Becco Contractors, Inc., and approve and authorize execution of a construction contract for the Base Bid and Alternates 1 and 2 for Kenosha: Garnett to Aspen Mill and Overlay