LEGISLATIVE RESEARCH CENTER
File #: 17-1830    Name:
Type: Consent Item Status: Passed
File created: 2/8/2017 In control: Broken Arrow City Council
On agenda: 2/21/2017 Final action: 2/21/2017
Title: Approval of bids received, award the lowest responsible bid to Magnum Construction, Inc., and authorization to execute a construction contract for Arrowhead Park Softball Shade Structures (Project No. 166014)
Attachments: 1. 170202 Certified Bid Tab Arrowhead Shade Structures

Broken Arrow City Council

                                                                                               Meeting of: 02-21-17

                                                                                    

To:                     Mayor and City Council

From:                     Engineering and Construction Department

Title: 

title

                     Approval of bids received, award the lowest responsible bid to Magnum Construction, Inc., and authorization to execute a construction contract for Arrowhead Park Softball Shade Structures (Project No. 166014)

End

Background:

When the contract for expansion of the Arrowhead Park Softball Fields was awarded in 2012, the wrap-around shade structures over the dugouts and bleachers were not included due to funding limitations.  Funds for the shade structures were budgeted this year, and a contract to provide and install them was advertised for bids on January 11 and 18, 2017.  Bids were opened on February 1, 2017.  Four bids were received.  The low bidder was Magnum Construction Inc., with a bid of $86,400.00.  The engineer’s estimate was $76,000.00.  The certified bid tabulation is attached.  Staff recommends award of the Arrowhead Park Softball Shade Structures to Magnum Construction Inc. in the amount of $86,400.00.

 

Funds for the work are available in Parks Capital Improvements.

 

Cost:                                                                $86,400.00

Prepared By:                                           Alex M. Mills, P.E., CFM, Engineering and Construction Director

Reviewed By:                                          Parks Department
                                    Finance Department
                                    City Attorney
                                    Assistant City Manager - Operations

 

Approved By:                      Michael L. Spurgeon, City Manager
                                  

Attachments:                                          Certified Bid Tabulation

Recommendation:

Award the lowest responsible bid, and authorize execution of a construction contract for Arrowhead Park Softball Shade Structures