Broken Arrow Municipal Authority
Meeting of: 01-03-17
To: Chairman and Authority Members
From: Department of Engineering and Construction
Title:
title
Ratification and approval of Change Order No. 3 with Triangle Construction and Utility, LLC, Aspen Creek Relief Line Contract No. S.1307
End
Background:
The Aspen Creek Relief Line, although a Broken Arrow Municipal Authority (BAMA) contract, is funded by both Vision 2025 surplus and BAMA Sewer Excess Capacity Fee funds. Approval of Change Order No. 3 (attached) was mistakenly entered as a City Council Consent Agenda item and was approved by the City Council. Staff requests that the BAMA ratify the City Council’s approval and subsequent execution of Change Order No. 3.
Cost: $9,924.50
Prepared By: Alex Mills, Director of Engineering and Construction
Reviewed By: Utilities Department
Finance Department
Assistant City Manager-Operations
Legal Department
Approved By: Michael L. Spurgeon, City Manager
Attachments: Professional Consultant Agreement
Recommendation:
Ratify and approve Change Order No. 3.