Title: Acceptance of a General Warranty Deed, Utility Easement, and Temporary Construction Easement conveyed to the City of Broken Arrow a tract of land that is part of Lot Four (4), Block Two (2), Lemon Addition, an addition to the City of Broken Arrow, Tulsa County, State of Oklahoma, according to the recorded plat thereof for the 9th Street widening from Elgin to El Paso (Project No. ST1210)
Attachments: 1. 9 Davis General Warranty Deed, 2. 9.1 Davis Utility Easement, 3. 9.1 Davis Temporary Construction Easement

Broken Arrow City Council

                                                                                               Meeting of: 10-04-16

                                                                                    

To:                     Mayor and City Council

From:                     Department of Engineering and Construction

Title: 

title

                     Acceptance of a General Warranty Deed, Utility Easement, and Temporary Construction Easement conveyed to the City of Broken Arrow a tract of land that is part of Lot Four (4), Block Two (2), Lemon Addition, an addition to the City of Broken Arrow, Tulsa County, State of Oklahoma, according to the recorded plat thereof for the 9th Street widening from Elgin to El Paso (Project No. ST1210)

End

Background:

The attached General Warranty Deed, Utility Easement, and Temporary Construction Easement conveyed to the City of Broken Arrow from Ann M. Davis, a single person.

 

Payment for the Temporary Construction Easement includes a temporary construction easement over the Permanent Utility Easement of 806 sf. Staff has reviewed this action and recommends approval.

 

Funding for this project is from 2011 G.O. Bond Issue.


Cost:                                                                General Warranty Deed: 434 SF @ $3.00 SF = $1,302
                                    Permanent Utility Easement: 806 SF @ $3.00/SF X 75% = $1,814
                                    Temporary Construction Easement: 806 SF @ $3.00/SF X 25%= $605
                                    Damages: $14,380.00
                                    Total Compensation Amount (Rounded): $  18,100.00              
                

Prepared By:                                           Alex M. Mills, P.E., Director of Engineering and Construction

 

Reviewed By:                                          Engineering and Construction Department
                                    Finance Department
                                    Assistant City Manager
                                    Legal Department                              

Approved By:                      Michael L. Spurgeon, City Manager                                    

Attachments:                                          General Warranty Deed
                                    Utility Easement
                                    Temporary Construction Easement                                                  

Recommendation:                     Accept the General Warranty Deed, Utility, and Temporary Easements                                                                   conveyed to the City of Broken Arrow