Broken Arrow City Council
Meeting of: 08-16-16
To: Mayor and City Council
From: Engineering and Construction Department
Title:
title
Acceptance of a Utility Easement and Temporary Construction Easement for Lots Six (6) and Seven (7), Block One (1), East Haskell Addition to the City of Broken Arrow, Tulsa County, State of Oklahoma, according to the recorded plat thereof for the 9th Street Widening from Elgin to El Paso (Project No. ST1210)
End
Background:
The attached Utility Easement, and Temporary Construction Easement conveyed to the City of Broken Arrow from Charlett R. Roach, a single person.
Payment for the Temporary Construction Easement includes a temporary construction easement over the Permanent Utility Easement of 670 sf, as well as an additional standalone temporary construction easement of 670 sf.
Staff has reviewed this action and recommends acceptance.
Funding for this project is from 2011 General Obligation Bond.
Cost: Permanent Utility Easement: 670 SF @ $3.00/SF X 75% = $1,508.00
Temporary Construction Easement: 1,340 SF @ $3.00/SF X 25%= $1,005.00
Damages: $4,187.00
Total Compensation Amount (Rounded): $ 6,700.00
Prepared By: Alex M. Mills, P.E., Director of Engineering and Construction
Reviewed By: Engineering and Construction Department
Finance Department
Assistant City Manager-Operations
Legal Department
Approved By: Michael L. Spurgeon, City Manager
Attachments: General Warranty Deed
Utility Easement
Temporary Construction Easement ...