LEGISLATIVE RESEARCH CENTER
File #: 24-139    Name:
Type: Consent Item Status: Agenda Ready
File created: 1/9/2024 In control: Broken Arrow City Council
On agenda: 1/16/2024 Final action:
Title: Notification of City Manager's execution of Change Orders on Public Construction Contracts as Authorized per Resolution 1439
Attachments: 1. 196031_Elam_Park_-_Change_Order__3
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow City Council

Meeting of: 01-16-2024

 

Title:

title

Notification of City Manager's execution of Change Orders on Public Construction Contracts as Authorized per Resolution 1439

End

Background:

The City of Broken Arrow has authorized the City Manager, per Resolution 1439, to execute public construction project change orders up to $40,000.00 or 10% of any one contract, whichever is less.

In an effort to keep the governing body and the public apprised of administration’s contractual actions.  Staff is submitting the public construction contract change orders for notification purposes only.

The City Manager has approved and executed the following:

1)                     Project # 196031 - Elam Park Phase I

Construction Contract Change Order #3 - $4,025.00

 

 

No further action is required by Council.

 

Cost:                                                                1:  $4,025.00

Funding Source:                     1: 2018 GO Bond

Requested By:                      Kenneth D. Schwab, PE, Acting Director of Engineering and Construction

Approved By:                      City Manager’s Office

Attachments:                                          1: 196031 Elam Park Ph. 1 - Change Order #3

                     

                 

Recommendation:

recommend

No Action Required

end