Background:
The Old Town Houston Street Waterline bore and Stormwater Improvements project is replacing sidewalk and waterline on the north side of Houston St between 1st and 9th. The project also is adding storm sewer pipes and regrading to be shallow ditches along the north side of Houston.
Change Order #1 addresses the following additions/deletions/changes to the contract:
- Install 4” concrete sidewalk, 6” concrete driveway, 18” CPP, Type AA4 End Treatment, Removal of Concrete Driveways, Urban ROW restoration, 36” CPP, and traffic control.
Total time added to contract is:
- 60 Days
The total cost for Change Order #1 amounts to $363,535.00
The additional cost associated with these changes is as follows:
Previous Change Orders: $0
This Change Order(s): $363,535.00
Total Cost of Change Orders: $363,535.00
Original Contract Amount: $565,940
Revised Contract Amount: $929,475.00
Percent Change in Contract: 64.24%
Applicable to Comp. Bid Act: 6.89% Max 15%
Cost: $363,535.00
Funding Source: 2018 GO Bond
Requested By: Charlie Bright, PE, Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: Old Town Houston Ditches Change Order 1
Recommendation:
recommend
Approval of and authorization to execute Change Order #1 with Gober Construction for the Old Town Houston Stormwater Improvements project (SW26010)