Broken Arrow City Council
Meeting of: 4-15-2025
Title:
title
Approval of and authorization to execute Change Order No. 1 with Muscat Co for the Paint Existing Traffic Signals (9399350)
End
Background:
The Paint Existing Traffic Signals project is to paint traffic signal poles across the city of Broken Arrow.
Change Order #1 addresses the following additions/deletions/changes to the contract:
- Contractors current work time per the contract is 7 am to 7pm. Contractor is requesting to work 12am to 5 am to be able to power wash the traffic signals. This will make it safer for vehicles to not have debris fall on their vehicle during the washing of the traffic signal poles.
- No time added, no cost change.
The total cost for Change Order #1 amounts to $0.00
The additional cost associated with these changes is as follows:
Previous Change Orders: $0.00
This Change Order(s): $0.00
Total Cost of Change Orders: $0.00
Original Contract Amount: $0.00
Revised Contract Amount: $0.00
Percent Change in Contract: 0.00%
Applicable to Comp. Bid Act: 0.00%
Cost: $0.00
Funding Source: 2018 GO Bond
Requested By: Charlie Bright, PE, Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: Paint Existing Traffic Signals
Recommendation:
recommend
Approval of and authorization to execute Change Order #1 with Muscat Co for the Paint Existing Traffic Signals (9399350)
end