Broken Arrow City Council
Meeting of: 03-24-2026
Title:
title
Acceptance of the Drainage Advisory Committee’s recommendation to approve expenditure of 2018 General Obligation Bond funds to design drainage design improvements from 3729 South 195th East Avenue to East 37th Court South
End
Background:
The project at 3729 South 195th East Ave. is currently in design for drainage improvements of the existing drainage system. The project is redirecting most of the storm runoff underground with a shallow grassed overflow channel.
Stormwater flows from E 37th Ct. to the inlet by means of a concrete channel in an easement across 4 properties. The concrete channel leading to the inlet has a history of maintenance concerns.
Staff requested $35,000.00 of the 2018 GO Bond, Proposition 6 for design costs at the 07-29-2024 Drainage Advisory Committee Meeting (Case Number 24-011) and was recommended for approval. Council approved the recommendation on 08-20-2024.
A contract with Cross Timbers Consulting was executed for a total amount of $42,755.00 by Council on 05-20-2025. Staff is requesting an additional $7,755.00 of the 2018 General Obligation Bond Proposition 6 funds to cover the design contract amount.
This area flows to Spunky Creek.
Cost: $7,755.00
Funding Source: 2018 General Obligation Bond, Proposition 6
Requested By: Charlie Bright, P.E., Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: Drainage Report, Exhibits
Recommendation:
recommend
Accept the Drainage Advisory Committee’s recommendation to approve the expenditure of 2018 General Obligation Bond funds to design drainage improvements from 3729 South 195th East Ave to East 37th Court Southend