Title: Acceptance of the Drainage Advisory Committee's recommendation to reject expenditure of 2018 GO Bond, Proposition 6 funds for the repair and replace of a wood retaining wall (Case No 24-003)
Attachments: 1. 24-003 2417 W Fort Worth
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow City Council

Meeting of: 05/07/2024

 

Title:

title

Acceptance of the Drainage Advisory Committee’s recommendation to reject expenditure of 2018 GO Bond, Proposition 6 funds for the repair and replace of a wood retaining wall (Case No 24-003)

End

 

Background:

The proposed project is behind 2417 W Fort Worth St in the Country Aire II subdivision. The project would be to replace an existing retaining wall on private property. Another option would be to grade and riprap the area.

Staff investigated the site and found that the retaining wall in in need of maintenance. The applicant asked the City to help repair the wall. Staff found no public benefit to the repair.

The estimated construction cost to build a new retaining wall is approximately $150,000.00 and the design cost would be approximately $50,000.00 in 2024 Dollars.

Repairing or replacing the existing retaining wall does not have a public benefit.

This area flows to Haikey Creek.

On April 29, 2024, the Drainage Advisory Committee reviewed the applicants request for funds and agreed with staff’s assessment that mitigating the erosion on private property does not provide a public benefit for the expenditure of public funds.  Therefore, the Drainage Advisory Committee recommends rejecting the applicants request for funds.

 

Cost:                                                                $0

Funding Source:                     2018 GO Bond, Proposition 6

Requested By:                      Charlie Bright, Director of Engineering and Construction

Approved By:                      City Manager’s Office

Attachments:                                          Drainage Project Report, Exhibits

 

Recommendation:

recommend

Accept the Drainage Advisory Committee’s recommendation to reject expenditure of 2018 GO Bond, Proposition 6 funds for the repair and replacement of a wood retaining wall.

end