Precision Project Management has completed the construction for Village at 1Eleven project. The required improvements are in accordance with approved construction plans and appropriate construction documents. These improvements have been constructed under the supervision of the City of Broken Arrow, Department of Engineering and Construction.
Said Improvements are for the sanitary sewer and water installations.
The owner desires to donate the public improvements identified above to the City of Broken Arrow. These improvements have an approximate value of $385,545.00
Cost: $0
Funding Source: N/A
Requested By: Kenneth D. Schwab, P.E., S.E., CFM, Interim Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: COBA Infrastructure Inventory - Village at 1Eleven
Recommendation:
recommend
Approve and authorization for final acceptance and donation of the public improvements at Village at 1Eleven located at 111th and Aspen Avenue