Title: Approval of and authorization to execute a Professional Services Contract with Olsson Associates, Inc., for Design of Repairs to Hillside Park Retaining Wall (Tiger Hill - southwest corner of Kenosha Street and Lynn Lane)
Attachments: 1. 151016 Prof Svcs Contract Olsson Hillside Park Retaining Wall

Broken Arrow City Council
Meeting of: 11-09-2015

To: Mayor and City Council
From: Department of Engineering and Construction
Title:
title
Approval of and authorization to execute a Professional Services Contract with Olsson Associates, Inc., for Design of Repairs to Hillside Park Retaining Wall (Tiger Hill - southwest corner of Kenosha Street and Lynn Lane)
End
Background:
Following the partial collapse of the Flight Safety retaining wall on the east side of Tiger Hill at Kenosha Street (71st Street South) and 9th Street (Lynn Lane) in May 2015, Engineering and Construction (E&C) Department contracted with Olsson Associates, Inc., to conduct a geotechnical investigation of the wall that the City constructed on the north side. Olsson's report was submitted August 6, 2015. The report contained general recommendations for remedial action to prevent failure of the City wall. The E&C Department requested Olsson to submit a proposal for development of remedial plans for repair or replacement of the wall, and after the submittal of their proposal of hourly costs not to exceed $19,480.00, the attached Professional Services Contract was prepared.

Funding for the design and construction work for the fountain will be from Sales Tax Capital Improvements. Staff recommends that the Council approve the Professional Services Contract and authorize its execution.

Cost: Not to Exceed $19,480.00
Prepared By: Douglas L. Tiffany, P.E., Director of Engineering and Construction
Reviewed By: Finance Department
Legal Department
Assistant City Manager

Approved By: Michael L. Spurgeon, City Manager
Attachments: Professional Services Contract with Olsson Associates, Inc.

Recommendation:
Approve the Professional Services Contract with Olsson Associ...

Click here for full text