Title: Approval of and authorization to execute a Professional Consultant Agreement with HDR Engineering, Inc. for Verdigris River Water Treatment Plant Raw Water Pump Station Improvements (Project No. 2454140)
Attachments: 1. 2454140 VRWTP Raw Water Pump Station Improvements Professional Consultant Agreement_Legal Signed
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Broken Arrow Municipal Authority

Meeting of: 06-17-2024

 

Title:

title

Approval of and authorization to execute a Professional Consultant Agreement with HDR Engineering, Inc. for Verdigris River Water Treatment Plant Raw Water Pump Station Improvements (Project No. 2454140)

End

 

Background:

The Verdigris River Water Treatment Plant Raw Water Pump Station currently has three pumping units with capacity of approximately 8.5 Million Gallons per Day (MGD) each. To prepare for future growth in the City of Broken Arrow two additional pumps will be added. This project is for the design of two additional vertical turbine raw water pumping units, Pumps #4 and #5, to the existing Verdigris River Water Treatment Plant Pump Station and includes the associated electrical and instrumentation and control improvements to support the proposed pumps. HDR Engineering, Inc. will design these improvements.

The Verdigris River Water Treatment Plant Raw Water Pump Station Improvements Agreement has been negotiated with HDR Engineering, Inc. for $174,696.000.

 

Cost:                                                                $174,696.00

Funding Source:                     Utilities Budget

Requested By:                      Charlie Bright, P.E., Director of Engineering & Construction

Approved By:                      City Manager’s Office

Attachments:                                          The VRWTP Raw Water Pump Station Improvements Professional Agreement

 

Recommendation:

recommend

Approve and authorize execution of a Professional Consultant Agreement with HDR Engineering, Inc. for Verdigris River Water Treatment Plant Raw Water Pump Station Improvements (Project No. 2454140).