Approval of and authorization to execute Change Order No. 1 with Ascend Commercial Builders for the Broken Arrow Public Works Field Office Project (2217090)
End
Background:
The BA Public Works Field Office project is to renovate the building for field services personnel
Change Order No. 1 addresses the following additions/deletions/changes to the contract:
- To install Fire suppression, electrical, and fire alarm panels within the building. All work to extend fire suppression, fire alarm panels, egress, and exit lighting to the warehouse area. The electrical work is included.
- There is a 55 day change in contract time.
The total cost for Change Order No. 1 amounts to $102,670.57
The additional cost associated with these changes is as follows:
Previous Change Orders: $0
This Change Order(s): $102,670.57
Total Cost of Change Orders: $102,670.57
Original Contract Amount: $1,700,314.98
Revised Contract Amount: $1,802,985.55
Percent Change in Contract: 6.04%
Applicable to Comp. Bid Act: 6.04%
Cost: $1,802,985.55
Funding Source: 2018 GO Bond
Requested By: Charlie Bright, PE, Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: BA Public Works Field Office Change Order 1
Recommendation:
recommend
Approve and authorize execution of Change Order No. 1 with Ascend Commercial Builders for the Broken Arrow Public Works Field Office Project (2217090)