Broken Arrow Drainage Advisory Committee
Meeting of: 07-27-26
Title:
title
Authorization to close project SW21030 Stonewood Crossing Drainage Improvements and return the $8,825.00 of the 2018 General Obligation Bond funds to the appropriate basin. Original Agenda Item Numbers 19-1311 and 21-693
End
Background:
The project SW21030 Stonewood Crossing Drainage Improvements was to mitigate drainage concerns in the Stonewood Crossing One and Two subdivisions.
Council approved $22,000.00 for survey and design, as well as $65,000.00 for construction. $87,000.00 of 2018 General Obligation Bond funds were approved for the project.
The project was designed in house and bid out for construction.
The final cost of the project was $93,040.28 with $14,865.28 coming out of the Stormwater capital fund for work that was performed within the Right of Way. A total of $78,175.00 of funds was spent from the Drainage Advisory Committee funds resulting in a balance of $8,825.00 for the project.
This is in the Haikey Creek Basin
Cost: $0.00
Funding Source: 2018 GO Bond, Proposition 6
Requested By: Charlie Bright, P.E., Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: Project Close Out Form
Recommendation:
recommend
Authorize the closing of the project SW21030 Stonewood Crossing Drainage Improvements and return the $8,825.00 of the 2018 General Obligation Bond funds to the appropriate Basin. Original Agenda Item numbers 19-1311 and 21-693
end