Broken Arrow City Council
Meeting of: 4-15-2025
Title:
title
Approval of and authorization to execute Change Order No. 1 with Anytime Roofing Inc. for the Old Fire Station No. 7 Roof Replacement (2417020)
End
Background:
The Old Fire Station #7 Roof Replacement project is to replace the old rock roof with a new metal roof.
Change Order #1 addresses the following additions/deletions/changes to the contract:
- Replace rotten wood nailers on the perimeter of the roof, the old on were too rotten to reuse.
The total cost for Change Order #1 amounts to $1,544.55
The additional cost associated with these changes is as follows:
Previous Change Orders: $0.00
This Change Order(s): $1,544.55
Total Cost of Change Orders: $1,544.55
Original Contract Amount: $103,460.54
Revised Contract Amount: $105,005.09
Percent Change in Contract: 1.49%
Applicable to Comp. Bid Act: 1.49%
Cost: $105,005.09
Funding Source: STCI
Requested By: Charlie Bright, PE, Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: Replace wood nailers CO 1
Recommendation:
recommend
Approve and authorize execution of Change Order No. 1 with Anytime Roofing Inc. for the Old Fire Station No. 7 Roof Replacement (2417020)
end