Broken Arrow Drainage Advisory Committee
Meeting of: 11-16-26
Title:
title
Acceptance of the Drainage Advisory Committee’s recommendation to close project SW25080 Bristol Ponds and return the remaining 2018 General Obligation Bond funds to the appropriate basin
End
Background:
The project Bristol Ponds was to assist with mitigation of erosion and erosive velocities in a drainage channel in the Bristol Ponds subdivision.
An outside engineer was contracted to perform the design for $44,560.32.
Construction of the mitigation efforts was completed for $198,865.00.
The resulting balance in the project budget is $36,574.68.
The original Committee agenda item is 24-1462, The original Council agenda item is 24-1506
This project drains to the Haikey Creek Basin
Cost: $0.00
Funding Source: 2018 GO Bond, Proposition 6
Requested By: Charlie Bright, P.E., Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: 20260729 SW25080 Bristol Ponds Closeout
Recommendation:
recommend
Accept the Drainage Advisory Committee Recommendation to close the project SW25080 Bristol Ponds and return the remaining 2018 General Obligation funds to the appropriate Basin
end