Broken Arrow City Council
Meeting of: 05-06-2025
Title:
title
Approval of and authorization to execute Change Order No. 1 with Gober Construction LLC for the Concrete Panel Replacement Turtle Creek Phase 2 (ST23030)
End
Background:
The Concrete Panel Replacement Turtle Creek Phase 2 project is to rehabilitate the neighborhood concrete streets.
Change Order #1 addresses the following additions/deletions/changes to the contract:
- Remove and replace a section of the French drains that are attached to the curb and gutter and reconnect them to the curb.
- Lowering of the inlet box to allow water to drain.
The total cost for Change Order #1 amounts to $6000.00
The additional cost associated with these changes is as follows:
Previous Change Orders: $0.00
This Change Order(s): $6,000.00
Total Cost of Change Orders: $6,000.00
Original Contract Amount: $525,489.00
Revised Contract Amount: $531,489.00
Percent Change in Contract: 1.14%
Applicable to Comp. Bid Act: 1.14%
Cost: $531,489.00
Funding Source: STCI
Requested By: Charlie Bright, PE, Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: Turtle Creek Phase 2 CO 1
Recommendation:
recommend
Approval of and authorization to execute Change Order No. 1 with Gober Construction LLC for the Concrete Panel Replacement Turtle Creek Phase 2 (ST23030)
end