Consideration, discussion, and possible action to recommend to City Council to expend funds to design improvements to NEEDA Pond (Case No. 24-013)
End
Background:
The proposed project is to investigate the functionality and design improvements for NEEDA Pond.
Staff investigated the site and found that the pond appears overgrown, and debris has collected near the inlet and outlet structures, thereby holding water. The pond was originally designed as a dry facility.
Staff is requesting $50,000.00 of the 2018 GO Bond, Proposition 6 for design costs.
This area flows to Haikey Creek.
Cost: $50,000.00
Funding Source: 2018 GO Bond, Proposition 6
Requested By: Charlie Bright, P.E., Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: Drainage Report, Exhibits
Recommendation:
recommend
Recommend to City Council the expenditure of funds to design improvements to NEEDA Pond