Broken Arrow City Council
Meeting of: 2-4-2025
Title:
title
Approval of and authorization to execute Change Order No. 2 with Ascend Commercial Builders for the BA Public Works Field Office Project (2217090)
End
Background:
The BA Public Works Field Office project is to renovate the building for field services personnel
Change Order #2 addresses the following additions/deletions/changes to the contract:
- To Demolish the existing insulation and add in Spray foam insulation. The insulation will be an 8 inch open cell foam on the roofline for an R-30 Value.
- There is a 5-day change in contract time.
The total cost for Change Order #2 amounts to $28,503.29
The additional cost associated with these changes is as follows:
Previous Change Orders: $102,670.57
This Change Order(s): $28,503.29
Total Cost of Change Orders: $131,173.86
Original Contract Amount: $1,700,314.98
Revised Contract Amount: $1,831,488.84
Percent Change in Contract: 7.71%
Applicable to Comp. Bid Act: 7.71%
Cost: $1,831,488.84
Funding Source: 2018 GO Bond
Requested By: Charlie Bright, PE, Director of Engineering and Construction
Approved By: City Manager’s Office
Attachments: BA Public Works Field Office Change Order 2
Recommendation:
recommend
Approve and authorize execution of Change Order #2 with Ascend Commercial Builders for the BA Public Works Field Office Project (2217090)
end