Broken Arrow City Council
Meeting of: 11-01-2016
To: Mayor and City Council
From: Department of Engineering and Construction
Title:
title
Notification of Change Orders with a value of less than $25,000 on public contracts
End
Background:
The City Manager or his designated representative has the authority to execute contracts, change orders, and work orders with a total increase in value of less than $25,000. Attached are the change orders, that have been executed since the last City Council meeting. No action is required. This item is for information only.
Cost: As noted on the attached documents
Prepared By: Alex Mills, P.E., Director of Engineering and Construction
Reviewed By: Finance Department
Legal Department
Assistant City Manager-Operations
Approved By: Michael L. Spurgeon, City Manager
Attachments: Change Orders:
City Hall Renovation Entry Plaza Planter Walls
Contract Number 151703B, Magnum Construction
Change Order C01 - $18,600.00.
Recommendation: No action required